The threshold markings are
The least dimension in case of a circular column of diameter D is taken as
The maximum permissible size of aggregates to be used in casting the ribs of a slab, is
The coefficient of hardness of stones used in road work should be greater than
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having