Mathematics Chain Rule Difficulty: Medium

30 labourers working 7 hours a day can finish a piece of work in 18 days. If the labourers work 6 hours a day, then the number of labourers to finish the same piece of work in 30 days, will be ?

Select the correct option to test your answer:

More Mathematics Questions

If the occurrence of one event means that another cannot happen, then the events are Gauri went to the stationers and bought things worth Rs. 25, out of which 30 paise went on sales tax on taxable purchases. If the tax rate was 6%, then what was the cost of the tax free items? One of the diagonals of a rhombus is double the other diagonal. Its area is 25 sq. cm. The sum of the diagonal is ? If 40 men or 60 women or 80 children can do a piece of work in 6 months, then 10 men, 10 women and 10 children together do the work in ? How old are you if you are born in 1995?