Mathematics
Time And Work
Difficulty: Medium
A and B together can complete a work in 12 days. B and C together can complete the same work in 8 days and A and C together can complete it in 16 days. In total, how many days do A, B and C together take to complete the same work ?
More Mathematics Questions
A tree is cut partially and made to fall on ground. The tree however does not fall completely and is still attached to its cut part. The tree top touches the ground at a point 10m from foot of the tree making an angle of 30°. What is the length of the tree?
What does Rs. 250 amounts to in 2 years with compound interest at the rate of 4% in the 1 st year and 8% in the second year ?
An old man driving bike at 80 km per hour. However being sugar patient, old man could not travel continuously. He takes small breaks each of 2 minutes for every 15 minute of his drive. How much distance the old man will cover in 90 minutes?
If the chance that a vessel arrives safely at a port is $$\frac{{9}}{{10}}$$ then what is the chance that out of 5 vessels expected at least 4 will arrive safely?
A bag contains an equal number of one rupee, 50 paise and 25 paise coins. If the total value is Rs. 35, how many coins of each type are there?