Mathematics Time And Work Difficulty: Medium

A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is ?

Select the correct option to test your answer:

More Mathematics Questions

Average of a, b, and c is 11; average of c, d and e is 17; average of e and f is 22 and average of e and c is 17. Find out the average of a, b, c, d, e and f. The average of two numbers is 6.5 and square root of their product is 6. What are the numbers? The value of a machine depreciates at the rate of 12 percent per annum. It was purchased three years ago. Its present value is Rs. 29644.032. What was the purchase price of the machine ? What rate present does a man get for his money when in discounting a bill due 10 months hence he deducts 10% of the amount of the bill ? In ΔABC, ∠A = 52° and O is the orthocentre of the triangle (BO and CO meet AC and AB at E and F respectively when produced). If the bisectors of ∠OBC and ∠OCB meet at P, then the measure of ∠BPC is: