Select the correct option to test your answer:
Mathematics
Time And Work
Difficulty: Medium
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only $${\frac{5}{8}}$$ th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?
More Mathematics Questions
If the six digit number 15x1y2 is divisible by 44, then (x + y) is equal to:
16 men can finish a piece of work in 49 days. 14 men started working and 8 days they could finish certain amount of work. If it is required to finish the remaining work in 24 days. How many more men should be added to the existing workforce ?
Two right angled triangles are congruent if : I. The hypotenuse of one triangle is equal to the hypotenuse of the other. II. A side for one triangle is equal to the corresponding side of the other. III. Sides of the triangles are equal. IV. An angle of the triangle are equal. Of these statements, the correct ones are combination of:
A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone then he do the work in ?
There are three boats A, B and C, working together they carry 60 people in each trip. One day an early morning A carried 50 people in few trips alone. When it stopped carrying the passengers B and C started carrying the people together. It took a total of 10 trips to carry 300 people by A, B and C. It is known that each day on an average 300 people cross the river using only one of the 3 boats A, B and C. How many trips it would take to A to carry 150 passengers alone?