Civil Engineering Construction Planning And Management Difficulty: Medium

Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float

Select the correct option to test your answer: