Civil Engineering Tunnel Engineering Difficulty: Medium

For transferring the tunnel alignment through shafts, we adopt the following steps: 1.Hanging two or more plumb lines in the shaft 2.Determining the bearing of the plumb lines i.e. plumb plane 3.Suspending a 35 kg weight by each plumb line 4.Immersing the weights of both the plumb lines in the buckets containing water The correct sequence of steps is:

Select the correct option to test your answer:

More Civil Engineering Questions

The maximum slenderness ratio of a compression member carrying both dead and superimposed load is In a consolidated drained test on a normally consolidated clay, the volume of the soil sample during shear The intensity of rain is expressed in The suitable cross-section of sewers to carry combined flow, is The self-cleansing velocity of water flowing through pipe lines, is