A mining project is composed of five activities whose three time estimates in months are given below: Activity Estimated duration (months) Optimistic time Most likely time Permissible time 1 - 2 1 1 7 1 - 3 2 5 8 2 - 4 1 1 7 3 - 4 2 5 14 4 - 5 3 6 15 The expected duration of the mining project in months is