X alone can complete a piece of work in 40 days. He worked for 8 days and left. Y alone completed the remaining work in 16 days. How long would X and Y together take to complete the work ?

Select the correct option to test your answer:

More Mathematics Questions

The compound interest on a certain sum of money at a certain rate for 2 years is Rs. 40.80 and the simple interest on the same sum is Rs. 40 at the same rate and for the same time. The rate of interest is = ? If p 3 - q 3 = (p - q) (p - q) 2 - xpq, then find the value of x : In the afternoon, a student read 100 pages at the rate of 60 pages per hour. In the evening, when she was tired, she read 100 more pages at the rate of 40 pages per hour. What was her average rate of reading the pages per hours ? If tan θ = 1, then the value of $$\frac{{8\sin \theta + 5\cos \theta }}{{{{\sin }^3}\theta - 2{{\cos }^3}\theta + 7\cos \theta }}$$ is? 40% of Raees marks is equal to 20% of Rahim's marks which percent is equal to 30% of Rehman's marks. If Rehman's marks is 80, then find the average marks of Raees and Rahim?