MCQ Practice
Chemical engineering plant cost index is used for finding the present cost of a particular chemical plant, if the cost of similar plant at some time in the past is known. The present cost of the plant = original cost times fracindex value at present index value at time original cost was obtained. The most major component of this cost index is
Subject: Chemical EngineeringTopic: Chemical Engineering Plant Economics
Correct Answer: A