X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

Select the best option to verify your answer:
Show Correct Answer
Correct Answer: Option A • $$13\frac{1}{3}$$ days

Related Mathematics Questions

In the given figure, O is centre of the circle. Circle has 3 tangents. If ∠QPR = 45°, then what is the value (in degrees) of ∠QOR? A working partner gets 20% as his commission of the profit after his commission is paid. If the working partner's commission is Rs. 8000, then what is the total profit in the business ? All the water in container A which was filled to its brim was poured into two containers B and C. The quantity of water in container B was 62.5% less than the capacity of container A. If 148 liters was now transferred from C to B, then both the containers would have equal quantities of water. What was the initial quantity of water in container A? If tanθ + cotθ = 2, then the value if tan 100 θ + cot 100 θ is? Sonia started a business investing Rs. 60000. After 6 months Vivek joined him with an amount of Rs. 140000. After 1 year Kirti also joined them with Rs. 120000. After 2 years the business yielded a total profit of Rs. 450000. What is the share of Vivek in the profit ?