MCQ Practice12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men do this work ?Subject: MathematicsTopic: Time And WorkA28 daysB36 daysC48 daysD52 daysCorrect Answer: BPractice QuizBack to MCQsRelated MCQsCurrent flows in a circuit whenEighttenths coulomb passes a point in 4 s. The current in amperes isThe unit of electrical charge is the