A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only frac58 th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are?
Subject: MathematicsTopic: Time And Work
Correct Answer: A