Twelve children take sixteen days to complete a work which can be completed by 8 adults in 12 days. After working for 3 days, sixteen adults left and six adults and four children joined them. How many days will they take to complete the remaining work?

Subject: MathematicsTopic: Time And Work
A

3 days

B

4 days

C

6 days

D

8 days

Correct Answer: C