X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last ?

Subject: MathematicsTopic: Basic Maths
A

6 days

B

10 days

C

15 days

D

20 days

Correct Answer: B