Construction Planning And Management MCQs
Practice Construction Planning And Management MCQs for competitive exams.
Construction Planning And Management MCQs
Practice questions from this topic.
Which one of the following is not an excavating and moving type of equipment?
Correct Answer: D
The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to
Correct Answer: C
The area under the Beta distribution curve is divided into two equal parts by
Correct Answer: D
The time which results in the least possible construction cost of an activity, is known as
Correct Answer: B
Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same
Correct Answer: A
Construction team means
Correct Answer: D
If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is
Correct Answer: A
Railway projects are treated as
Correct Answer: B
While filling the tender for any work, the contractor considers
Correct Answer: D
Whenever an activity has zero total float, then
Correct Answer: C
The direct cost of a project with respect to normal time is
Correct Answer: A
If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be
Correct Answer: C