Civil EngineeringConstruction Planning And Management MCQs
Practice Construction Planning And Management MCQs for competitive exams.
Construction Planning And Management MCQs
Practice questions from this topic.
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
- A. 1
- B. 2
- C. 3
- D. 4
Correct Answer: D
The Overall in-charge of an organization at the site responsible for the execution of the works, is
- A. Executive Engineer
- B. Engineer
- C. Junior Engineer
- D. Assistant Engineer
Correct Answer: B
The difference between the time avail-to do a job and the time required to do the job, is known as
- A. Event
- B. Float
- C. Duration
- D. Constraint
Correct Answer: B
Time and progress chart of a construction, is also known as
- A. Bar chart
- B. Gantt chart
- C. Modified Mile stone chart
- D. All the above
Correct Answer: D
For the network shown in the given figure, the expected time for the activity
- A. 1-2 is 4
- B. 2-3 is 7
- C. 3-4 is 8
- D. All the above
Correct Answer: D
For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
- A. 8 days
- B. 9 days
- C. 10 days
- D. 15 days
Correct Answer: B
The probability of completion of any activity within its expected time is
- A. 50 %
- B. 84.1 %
- C. 99.9 %
- D. 100 %
Correct Answer: A
A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be
- A. 15 minutes
- B. 20.143 minutes
- C. 21 minutes
- D. 27 minutes
Correct Answer: C
The first stage of a construction, is
- A. Preparation of estimate
- B. Survey of the site
- C. Initiation of proposal
- D. Preparation of tender
Correct Answer: C
If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
- A. 3.5 and (5)/(6)
- B. 5 and (25)/(36)
- C. 3.5 and (25)/(36)
- D. 4 and (5)/(6)
Correct Answer: C
A construction schedule is prepared after collecting
- A. Number of operations
- B. Output of labour
- C. Output of machinery
- D. All the above
Correct Answer: D
The normal time required for the completion of project in the above problem is
- A. 9 days
- B. 13 days
- C. 14 days
- D. 19 days
Correct Answer: C