Civil Engineering

Construction Planning And Management MCQs

Practice Construction Planning And Management MCQs for competitive exams.

Construction Planning And Management MCQs

Practice questions from this topic.

For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

  1. A. 1
  2. B. 2
  3. C. 3
  4. D. 4
Report Error

The Overall in-charge of an organization at the site responsible for the execution of the works, is

  1. A. Executive Engineer
  2. B. Engineer
  3. C. Junior Engineer
  4. D. Assistant Engineer
Report Error

The difference between the time avail-to do a job and the time required to do the job, is known as

  1. A. Event
  2. B. Float
  3. C. Duration
  4. D. Constraint
Report Error

Time and progress chart of a construction, is also known as

  1. A. Bar chart
  2. B. Gantt chart
  3. C. Modified Mile stone chart
  4. D. All the above
Report Error

For the network shown in the given figure, the expected time for the activity

  1. A. 1-2 is 4
  2. B. 2-3 is 7
  3. C. 3-4 is 8
  4. D. All the above
Report Error

For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is

  1. A. 8 days
  2. B. 9 days
  3. C. 10 days
  4. D. 15 days
Report Error

The probability of completion of any activity within its expected time is

  1. A. 50 %
  2. B. 84.1 %
  3. C. 99.9 %
  4. D. 100 %
Report Error

A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be

  1. A. 15 minutes
  2. B. 20.143 minutes
  3. C. 21 minutes
  4. D. 27 minutes
Report Error

The first stage of a construction, is

  1. A. Preparation of estimate
  2. B. Survey of the site
  3. C. Initiation of proposal
  4. D. Preparation of tender
Report Error

If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

  1. A. 3.5 and (5)/(6)
  2. B. 5 and (25)/(36)
  3. C. 3.5 and (25)/(36)
  4. D. 4 and (5)/(6)
Report Error

A construction schedule is prepared after collecting

  1. A. Number of operations
  2. B. Output of labour
  3. C. Output of machinery
  4. D. All the above
Report Error

The normal time required for the completion of project in the above problem is

  1. A. 9 days
  2. B. 13 days
  3. C. 14 days
  4. D. 19 days
Report Error