Civil EngineeringConstruction Planning And Management MCQs
Practice Construction Planning And Management MCQs for competitive exams.
Construction Planning And Management MCQs
Practice questions from this topic.
For the execution of a project, a contractor is
- A. A person
- B. A firm
- C. An agency
- D. All the above
Correct Answer: D
For a given size of bucket, the ideal output of a dragline will be least in
- A. Moist loam
- B. Sand and gravel
- C. Good common earth
- D. Wet sticky clay
Correct Answer: D
If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is
- A. 30 kg
- B. 300 kg
- C. 900 kg
- D. 1000 kg
Correct Answer: C
The time with which direct cost does not reduce with the increase in time is known as
- A. Crash time
- B. Normal time
- C. Optimistic time
- D. Standard time
Correct Answer: B
A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will
- A. Reduce by 200 kg
- B. Increase by 200 kg
- C. Increase by 250 kg
- D. Reduce by 250 kg
Correct Answer: A
A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be
- A. 20 kg/tonne
- B. 30 kg/tonne
- C. 40 kg/tonne
- D. 50 kg/tonne
Correct Answer: C
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
- A. fraca + m + b 6
- B. fraca + 2m + b 6
- C. fraca + 4m + b 6
- D. fraca + 5m + b 6
Correct Answer: C
A golden rule for the procurement of construction stones, suggests
- A. 100% at the site
- B. 67% at the site and 33% under procurement
- C. 50% at the site and 50% under procurement
- D. 33% at the site and 67% under procurement
Correct Answer: B
A critical ratio scheduling
- A. Determines the status of each activity
- B. Adjusts automatically changes in activity progress
- C. Is a dynamic system
- D. None of these
Correct Answer: D
The main principle of an organization, is
- A. Unity of command
- B. Effective control at all levels
- C. Delegation of authority
- D. All the above
Correct Answer: D
The main disadvantage of line organization, is
- A. Rigid structure
- B. Extraordinary delay in communications
- C. Top level executions over work
- D. All the above
Correct Answer: D
Various activities of a project, are shown on bar charts by
- A. Vertical lines
- B. Horizontal lines
- C. Dots
- D. Crosses
Correct Answer: B