The most popular type of organization used for Civil Engineering Constructions, is

  1. A. Line organization
  2. B. Line and staff organization
  3. C. Functional organization
  4. D. Effective organization
Report Error

The most suitable type of equipment for compaction of cohesive soils is

  1. A. Smooth-wheeled rollers
  2. B. Vibratory rollers
  3. C. Sheep foot rollers
  4. D. Tampers
Report Error

Slack time refers to

  1. A. An activity
  2. B. An event
  3. C. Both event and activity
  4. D. None of the above
Report Error

An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is

  1. A. Rs. 8,43,750
  2. B. Rs. 8,75,000
  3. C. Rs. 10,50,000
  4. D. Rs. 11,56,250
Report Error

Critical path lies along the activities having total float

  1. A. Positive
  2. B. Negative
  3. C. Zero
  4. D. Same
Report Error

Military organization is known as

  1. A. Line organization
  2. B. Line and staff organization
  3. C. Functional organization
  4. D. None of these
Report Error

Batching refers to

  1. A. Controlling the total quantity at each batch
  2. B. Weighing accurately, the quantity of each material for a job before mixing
  3. C. Controlling the quantity of each material into each batch
  4. D. Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Report Error

Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated.

  1. A. 1, 2 and 3 are correct
  2. B. 1 and 4 are correct
  3. C. 2, 3 and 4 are correct
  4. D. 1, 2 and 4 are correct
Report Error

Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities of project PERT is preferred for planning because of

  1. A. 1, 2 and 4
  2. B. 3, 4 and 5
  3. C. 1, 3 and 4
  4. D. 1, 2 and 5
Report Error

If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is

  1. A. 4 days
  2. B. 6 days
  3. C. 10 days
  4. D. 16 days
Report Error

Works costing less than Rs. 20,000 are treated as

  1. A. Any project
  2. B. Major projects
  3. C. Minor projects
  4. D. Petty works
Report Error

An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?

  1. A. Rs. 31050
  2. B. Rs. 34500
  3. C. Rs. 37950
  4. D. Rs. 50000
Report Error