Civil EngineeringConstruction Planning And Management MCQs
Practice Construction Planning And Management MCQs for competitive exams.
Construction Planning And Management MCQs
Practice questions from this topic.
While scheduling a project by C.P.M.
- A. A project is divided into various activities
- B. Required time for each activity is established
- C. Net work is drawn by connecting the activities and the events
- D. All the above
Correct Answer: D
The constraints in case of resource smoothening operation would be
- A. Resources
- B. Project duration time
- C. Both resources and project duration time
- D. None of the above
Correct Answer: B
If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be
- A. 2.3% and 84.1%
- B. 97.7% and 84.1%
- C. 97.7 % and 15.9%
- D. 15.9% and 97.7%
Correct Answer: A
The basic action involved in sheep foot rolling is
- A. Kneading
- B. Pressing
- C. Tamping
- D. Vibration
Correct Answer: A
The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is
- A. 3425 kg
- B. 5515 kg
- C. 4350 kg
- D. 2975 kg
Correct Answer: B
Wheeled tractors are replacing crawler tractors because 1. Wheeled tractors travel faster. 2. Crawler tractors are more expensive. 3. Track parts of a crawler wear out quickly. 4. Crawler tractors have stick control. of following statements
- A. 1, 3 and 4 are correct
- B. 2, 3 and 4 are correct
- C. 1, 2 and 3 are correct
- D. 1, 2 and 4 are correct
Correct Answer: C
Pick up the PERT event from the following:
- A. Digging of foundation started
- B. Digging of foundation completed
- C. Laying of concrete started
- D. All the above
Correct Answer: D
At a work site, statistical quality control of concrete means
- A. Measurement of risks to eliminate failures
- B. Applying the theory' of probability to sample testing or inspection
- C. Reduction in wastage of inspection costs
- D. Reduction in costs for the removal of defects
Correct Answer: B
In PERT analysis, the time estimates of activities and probability of their occurrence follow
- A. Normal distribution curve
- B. Poisson's distribution curve
- C. Beta distribution curve
- D. None of the above
Correct Answer: C
During the construction period, price variation clause in contracts caters to
- A. Increase in rates of only important materials
- B. Variation in cost in materials element, labour element and petrol-oil-lubricant element
- C. Variation in total cost of the project on an ad hoc basis
- D. Rate of inflation
Correct Answer: B
Which of the following is not a PERT event?
- A. Site investigation started
- B. Sessional work completed
- C. Bus starts from Jaipur
- D. Class is being attended
Correct Answer: D
Mobilization advance up to 10% of the cost of work is given to a contractor
- A. On commencement of work at site for payment of loan taken by him
- B. For the purchase of construction materials
- C. For the payment of advances to labour and other staff
- D. For all activities required to start the work at site on finalization of the contract document
Correct Answer: D