Construction Planning And Management MCQs
Practice questions from this topic.
What estimate would you give for the variance in above problem ?
- A. 81
- B. 54
- C. 36
- D. 9
Correct Answer: A
In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace?
- A. Yes, because of heavier overheads and handling cost
- B. Yes, because of the very high order of quality control for the factory made components
- C. No, because of repetitive manufacture of a number of elements
- D. No, because of savings in site labour
Correct Answer: C
PERT technique of network analysis is mainly useful for
- A. Small projects
- B. Large and complex projects
- C. Research and development projects
- D. Deterministic activities
Correct Answer: C
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
- A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
- B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
- C. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
- D. All the above
Correct Answer: D
The independent float affects only
- A. Preceding activities
- B. Succeeding activities
- C. The particular activity involved
- D. None of the above
Correct Answer: C
The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
- A. Event
- B. Free float
- C. Dummy
- D. Constraint
Correct Answer: C
If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
- A. EF = ES + D
- B. LS = LF - D
- C. LF = LS + D
- D. All the above
Correct Answer: D
The process of incorporating changes and rescheduling or replanning is called
- A. Resource levelling
- B. Resource smoothening
- C. Updating
- D. Critical path scheduling
Correct Answer: C
The time corresponding to minimum total project cost is
- A. Crash time
- B. Normal time
- C. Optimistic time
- D. Between normal time and crash time
Correct Answer: D
The salient feature of functional organization is
- A. Strict adherence to specifications
- B. Separation of planning and design part
- C. Each individual maintains functional efficiency
- D. All the above
Correct Answer: D
Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is
- A. 1, 2, 4, 3, 5
- B. 1, 3, 2, 4, 5
- C. 1, 2, 3, 4, 5
- D. 1, 3, 4, 2, 5
Correct Answer: C
Preliminary project report for a road project must contain
- A. The detailed estimated cost based on detailed design
- B. The several alternatives of the project that have been considered
- C. The soil survey, traffic survey, concept design and approximate cost
- D. The contract documents for inviting tenders
Correct Answer: C